ROAD CONSTRUCTION - SOUTH BRANCH ROAD (CR 567) BRIDGE C0701, BRANCHBURG

South Branch Road (CR 567) over Brokaw Brook, Branchburg Township
(UPDATE 1-8-2024) Construction Phase Stage 1 began on September 14, 2023, with new bridge and realigned roadway work being done while South Branch Road remains open to through traffic.  Utility relocation work in progress.  Construction Phase Stage 2 is tentatively scheduled to begin in March / April 2024, with up to a 51-calendar day full road closure with posted detour route.  County will provide advance updates when work progresses and Stage 2 full road closure schedule is confirmed.
More information on this project can be found here:  Replacement of County Bridge C0701 - South Branch Road